  Calculate workdays between dates using Excel
We're going to calculate how many workdays, considering the holidays, are there between two specific dates
 
  Author: mat | Version: 2010 | 24th September 2011 |  
 
 
1.
  Start the Microsoft Excel and enter the the data just like I did.
 
 
2.
  Click the cell next to Working days.
 
 
3.
  In the menu click Formulas.
 
 
4.
  And click the Insert Function button.
 
 
5.
  Select All for the category, choose the NETWORKDAYS function and click GO.
 
 
6.
  In the new window click Start_date field and the click the cell where you have your project start date, click End_date and click the cell with your end date.
 
 
7.
  Click the Holidays field ...
 
 
8.
  ... and select the cells with holiday entries.

Click OK.
 
 
9.
  And there's your result. Shouldn't be to hard to finish your project in time ;)
 
 
 
 